ZTR has completed mounting of 8 transformers in St. Petersburg

Major project for MES Northwest has been completed

Service center engineers of PJSC “Zaporozhtransformator” (ZTR) have completed mounting of 8 transformers at the s/s Vostochnaya (St. Petersburg, RF). Works as for comprehensive reconstruction of substation were held within the project MES Northwest.

ZTR has installed and mounted 4 two-phase autotransformers rated for 200 MVA 110 kV, two two-phase transformers rated for 25 MVA 110kV and two transformers for auxiliaries rated for 6.3 MVA 110kV at s/s Vostochnaya.

Mounting of the transformer equipment was started in the year 2010. All the transformers were delivered in the year 2009 in accordance to contract, concluded between ZTR and MES Northwest in the middle of the year 2008.

S/s Vostochnaya is to be the main section of power supply system in Leningrad and supplies energy to Kalininskiy, Krasnogvardeyskiy Vyborgskiy and Nevskiy districts of St. Petersburg, and also Vsevolzhskiy district of Leningradskaya region. Works on object reconstruction are planned to be completed in the year 2011 in accordance with information of press service JSC “FSK EES”.

16.05.2011